N10 — Implementation Backlog

PLANNING ONLY. No file modification, migration, deployment, or code execution is authorized before N11 approval and explicit user instruction to resume implementation.

Goal: Translate the closed business PRDs into small implementation slices with dependencies, UI/UX checkpoints, and acceptance tests.

Architecture: Keep Cloudflare Worker + Hono + D1 and the PersistenceAdapter seam. Work incrementally; do not replace the current MVP wholesale. Preserve manual WhatsApp payment and the approved customer-data boundary.

Tech stack: TypeScript, Hono, Cloudflare Worker, D1/SQLite, server-rendered views, existing tests and smoke tests.

Non-negotiable constraints

Dependency map

S01 baseline/test seams
  → S02 client profile + S03 auth
  → S04 public website/catalog
  → S05 availability + staff foundation
  → S06 booking/intake
  → S07 payment/Admin
  → S08 cancellation/refund/reschedule
  → S09 psychologist scope + staff hardening
  → S10 privacy/copy
  → S11 UAT/checklist

The staff foundation is deliberately available before payment and cancellation actions because those actions require StaffMembership, role checks, and actor_membership_id.

Slices

S01 — Freeze baseline and establish test seams

Purpose: Record the actual baseline before behavior changes.

Files: inspect mvp/app/src/, mvp/app/migrations/, mvp/tests/, mvp/package.json, mvp/scripts/smoke-test.sh.

Acceptance: known typecheck/build/test commands; remote smoke baseline recorded without changing production data; demo fixtures distinguished from production.

Test seams: frozen clock/fake timer, mock D1 adapter, test auth injection, mock evidence storage. These seams must be agreed before tests are written.

Dependency: none.

S02 — Client account and profile data

Purpose: Store Google identity separately from user-provided Nama Panggilan and persist all approved required profile/address fields.

Likely files: mvp/app/migrations/0004_client_profile.sql, mvp/app/src/domain/types.ts, mvp/app/src/persistence/adapter.ts, mvp/app/src/persistence/d1-adapter.ts, mvp/app/src/modules/client.ts.

Acceptance: incomplete profile blocks booking; client must be 18+ based on date of birth; Indonesian WhatsApp number is validated in E.164/approved local format; client can read/update only their own profile; fields have explicit purpose/privacy mapping; no extra fields added.

Test seam: MockAuthProvider identity + client ownership fixture.

Dependency: S01.

S03 — Google SSO client login gate

Purpose: Make authenticated identity mandatory for booking.

Likely files: mvp/app/src/modules/auth.ts, mvp/app/src/worker/index.ts, mvp/app/src/views/index.ts, mvp/wrangler.toml.

Acceptance: anonymous user sees Google login; callback binds identity; cancellation/replay/error cannot submit; no guest path; session ownership prevents cross-client access.

Test seam: local MockAuthProvider/session injection; no external Google OAuth in automated tests.

Dependency: S02.

S04 — Public website, navigation, and catalog

Purpose: Apply PRD-03 and catalog decisions to public pages.

Scope: Beranda, Layanan hover/focus submenu with four program briefs, List Psikolog, About, FAQ, placeholder assets, and catalog/pricing.

Likely files: mvp/app/src/modules/catalog.ts, mvp/app/src/views/index.ts, content/assets directories.

Acceptance: Beranda, Layanan, List Psikolog, About, FAQ; Layanan hover/focus submenu contains four programs; only individual counseling is bookable; Chat/Call/offline labels and prices correct; 100% Bahasa Indonesia; placeholders clearly marked; 360px mobile layout.

UI/UX checkpoint A: design public navigation, submenu, psychologist card, FAQ interaction, and placeholder asset treatment before implementation.

Dependency: S01; S02/S03 only if login CTA is included in this slice.

S05 — Availability, buffer, holidays, and staff foundation

Purpose: Generate valid slots and establish the minimum staff membership foundation required by Admin actions.

Boundary: Keep slot generation separate from staff authorization. The staff foundation here is only the membership schema, role enum, and test identity needed by later Admin commands; full staff security hardening is S09.

Likely files: mvp/app/src/modules/availability.ts, mvp/app/src/modules/auth.ts, mvp/app/src/persistence/*, mvp/app/migrations/0005_staff_membership_availability.sql, mvp/app/src/views/index.ts.

Acceptance: Monday–Sunday; public holidays and exceptions closed; windows 09.00–12.00 and 16.00–20.00 WIB; 60-minute sessions; 15-minute buffer-aware starts; 2-hour cutoff; same grid online/offline; overlap/expiry safe. Morning starts are exactly 09.00 and 10.30; evening starts are exactly 16.00, 17.30, and 18.45. StaffMembership foundation supports one Superadmin, Admin, and Psychologist.

Admin schedule capability: Admin can set public holidays, recurring closed days, and one-off slot withdrawal with an internal reason; the public slot list uses the same source of truth.

UI/UX checkpoint B: design slot list, closed-day state, empty state, cutoff message, and Admin holiday/withdrawal calendar.

Test seam: frozen clock, deterministic holiday calendar, concurrency fixture.

Dependency: S01, S03.

S06 — Required booking and intake form

Purpose: Enforce PRD-01 profile/intake contract in the booking flow.

Likely files: mvp/app/src/modules/booking.ts, mvp/app/src/views/index.ts, mvp/app/src/domain/types.ts, migration if needed.

Acceptance: all profile/address and intake fields required; client must be 18+; topics multi-select; problem description minimum 50 and max bounded; consent version stored; no clinical fields; OfferSnapshot/hold/reservation atomic.

UI/UX checkpoint C: design profile completion, grouped address fields, intake form, validation, consent, loading, error, and confirmation states.

Dependency: S02, S03, S04, S05.

S07 — Manual payment and post-verification invoice

Purpose: Implement PRD-02 with correct invoice ordering.

Likely files: mvp/app/src/modules/payment.ts, mvp/app/src/modules/admin.ts, mvp/app/src/views/index.ts, payment migration.

Acceptance: pre-verification view has preliminary instructions + WhatsApp link only; Admin records proof and checks bank/QRIS; verify/reject in dashboard; official PDF/text invoice only after verification; invoice excludes intake narratives; underpayment top-up; overpayment return evidence; B04 legacy payment/refund_action queries removed or reconciled to current schema.

UI/UX checkpoint D: design preliminary payment, pending state, rejection, underpayment, overpayment, verified invoice, and client confirmation states.

Test seam: mock evidence storage, fake clock, payment proof fixtures.

Dependency: S05 staff foundation, S06, S04.

S08 — Cancellation, refund, and Admin reschedule workflow

Purpose: Implement PRD-05 and the PRD-04 online↔offline change rule.

Likely files: mvp/app/src/modules/admin.ts, mvp/app/src/modules/booking.ts, mvp/app/src/views/index.ts, cancellation/refund/reschedule migration.

Acceptance: no public mutation endpoint; trigger is client_requested or psychologist_unavailable; required evidence matches trigger; statuses and audit work; refund completion requires transfer proof; Admin-mediated mode change creates RescheduleAction and updated OfferSnapshot; slot/capacity release follows rules; idempotent transitions.

UI/UX checkpoint E: design cancellation/refund queue, evidence upload, status history, provider-unavailable action, and reschedule adjustment.

Test seam: mock evidence storage + state-machine fixtures.

Dependency: S05 staff foundation, S07, S06.

S09 — Staff authorization and scoped psychologist view

Purpose: Complete role enforcement and customer-data whitelist.

Likely files: mvp/app/src/modules/auth.ts, mvp/app/src/modules/admin.ts, mvp/app/src/views/index.ts, staff migration.

Acceptance: one Superadmin; Admin; Psychologist; Google SSO + StaffMembership; placeholder auth disabled in production; psychologist query is restricted to booking.state = 'confirmed' and the authenticated psychologist's assigned bookings; psychologist receives only display name, WhatsApp, mode, slot, topics, non-clinical description, expected outcome, returning-client flag; excludes full address, religion, occupation, education, payment evidence; sharing audit includes actor, timestamp, booking, fields shared; last-admin/superadmin protections.

UI/UX checkpoint F: design scoped psychologist view and visibly separate Admin/Superadmin capabilities.

Test seam: role matrix fixture, mock auth, audit assertion.

Dependency: S03, S05, S07, S08.

S10 — Privacy, rights, copy, and operational hardening

Purpose: Apply PRD-06/07/08 to real routes and messages.

Likely files: mvp/app/src/views/index.ts, mvp/app/src/worker/index.ts, mvp/README.md, content assets.

Acceptance: Terms contains WhatsApp cancellation/refund rule; privacy/consent/safety placeholders clearly marked until replaced; client rights route to email; breach notice route exists; no marketing; error/log redaction; footer/FAQ/booking links work.

Dependency: S03, S06–S09.

S11 — UAT and lightweight launch checklist

Purpose: Execute PRD-08 without enterprise ceremony.

Likely files: docs/prd/08-launch-gates.md, mvp/scripts/smoke-test.sh, mvp/README.md.

Acceptance: A–G checklist distinguishes demo from real; e2e covers login → profile → booking → transfer proof → Admin verify → invoice → confirmation; blockers remain unchecked without evidence; sign-off records date/maintainer/open items.

Dependency: S01–S10.

UI/UX sequence

UI/UX is not last. It happens at each checkpoint:

  1. Before S02/S03: Google SSO login gate and Profile Completion (Profil Saya + Alamat Saya).
  2. Before S04: Public navigation, Layanan hover/focus submenu, psychologist card, FAQ, and placeholder assets.
  3. Before S05: Slot selection calendar, buffer-aware starts, closed-day states, cutoff notice, and Admin holiday/withdrawal calendar.
  4. Before S06: Booking summary, intake form, multi-topic selector, 50-character counter, consent/safety states.
  5. Before S07: Preliminary payment handoff and Admin Payment Verification Queue, including proof viewer and amount mismatch notes.
  6. Before S08: Admin Cancellation/Refund Queue, trigger selector, evidence upload, refund proof, and reschedule adjustment.
  7. Before S09: Scoped Psychologist View with the customer-data whitelist visibly enforced.

Each checkpoint must include a small wireframe/prototype, mobile review, states, and mapping to PRD acceptance criteria. Do not design deferred features.

N11 approval checklist

Before implementation begins: